Sunset and Tietan construction week-ahead update for July 10

Post Date:07/10/2019 1:30 PM

This is your week-ahead update for July 10 for the Sunset and Tietan construction work:

Sunset and Tietan construction before  

Premier Excavation is currently installing sewer main from Third Avenue to Modoc Street, upgrading the storm system at the intersection of Third Avenue and Tietan Street, and pouring curb, gutter, and sidewalk from Fourth Avenue to Third Avenue. Roundabout curb and sidewalk construction is scheduled to begin the week of July 19. Tietan Street is scheduled to be open to traffic prior to the Walla Walla County Fair.